| Deciding to buy a home is an enormous and life changing decision. | .
| This guide is designed to give you an idea of the processes involved and will vary slightly from builder to builder. |
| Your House & Land Package will consist of 2 separate contracts - one for the land and one for the house, which go together to form a package. |
| TIMING | ITEM | CLIENT REQUIREMENTS |
Week 1 |
Pay deposit on land and sign a contract - see Land Purchase Procedure |
Pay 0.25% deposit on land & sign contract. Make appointment with your Legal Representative for Land purchase |
Week 1-2 |
Builder to prepare formal quotation |
Request Quotation |
Week 2 -3 |
Pay deposit (or balance deposit) to builder and sign your quotation & pay balance of Land deposit |
Obtain formal loan approval from lender (1-2 weeks) |
Week 4 |
Builder proceeds to draw plans for Council & Statutory Authorities |
|
Week 5 - 6 |
Builder has Client sign plans and select colours with Builders Colour Consultant. Settle Land Purchase. |
Sign Plans, Complete Colour Selection & settle land purchase |
Week 7 - 12 |
Builder lodges plans for Council & Statutory Approvals and approvals obtained. |
Client to provide proof of ownership of Land to builder |
Week 10 - 12 |
Builder prepares Building Agreement for execution by Client |
Client signs building agreement & provides Authority from bank to commence construction |
Week 13 |
Builder completes final construction plans and places orders with suppliers |
|
Week 14 |
Construction Starts - 6 - 9 months until completion |
|
Approx Construction Payment Schedule* |
|
Initial Deposit |
$2,000 - $4,000 |
Balance of deposit |
5% |
Slab Complete |
20% - 25% |
Frame Complete |
25% - 30% |
Brickwork & Roof complete (Lockup) |
20% |
Internal Linings |
15% - 20% |
Completion & Handover |
5% - 10% |
* Varies from builder to builder |
|